#About this project

To improve navigational accessibility from the South Paray Wharf to Iririki Island, Hall Pacific dredged a channel 50m wide, 200m long and 5.5m deep (approximately 46,000m3).

Coral limestone material was used to reclaim part of the port for container space. This will allow 60-metre-long cargo ships to use the channel, cutting significant time off their voyage.

#Project Data

  • LOCATION

    Port Vila, Efate, Vanuatu

  • CLIENT

    Government of Vanuatu

#Related Projects

Lumsden Point Dredging Works

Ports & Harbours

Lumsden Point Dredging Works

Dredging of approximately 1.2 million cubic meters.

Bowen Entrance Channel Dredging

Ports & Harbours

Bowen Entrance Channel Dredging

Design, construction and dredging for a boat harbour and entrance channel.

Breakwater Marina Townsville Maintenance Dredging

Ports & Harbours

Breakwater Marina Townsville Maintenance Dredging

Dredging operations including the design and construction of dredge bunds pipeline.

Charles Point Patches

Ports & Harbours

Charles Point Patches

Dredging to increase the depth of a shipping channel in Darwin, NT.