Ross River Maintenance Dredging

Ross River Townsville, Queensland

Dredging from Ross River including the design and construction of dredge bunds.

Ross River Maintenance Dredging

#About this project

Hall Contracting was awarded the design and construction of a discharge pond to capture and manage the dredge discharge material from Ross River on the adjoining Port of Townsville. Once the bunds were in place, Hall Contracting commenced with the removal of approximately 100,000m3 of sediments from Ross River by the Cutter Suction Dredge ‘Everglade’. Hall Contracting developed a methodology to manage the dredge spoil by mixing, moving and stockpiling the dredge material to maintain discharge capacity in the pond.

At the completion of dredging, Hall Contracting then removed the discharge material from the pond and produced a reusable soil. This was achieved by mixing the collected fines with the collected courser material, creating an approximate 20%-80% mixture for re-use as requested by DTMR. The project had environmental performance objectives as conditioned by the Department of Environment and Heritage Protection which required daily monitoring.

#Project Data

  • LOCATION

    Ross River Townsville, Queensland

  • CLIENT

    Department of Transport and Main Roads (DTMR)

#Related Projects

Lumsden Point Dredging Works

Ports & Harbours

Lumsden Point Dredging Works

Dredging of approximately 1.2 million cubic meters.

Bowen Entrance Channel Dredging

Ports & Harbours

Bowen Entrance Channel Dredging

Design, construction and dredging for a boat harbour and entrance channel.

Breakwater Marina Townsville Maintenance Dredging

Ports & Harbours

Breakwater Marina Townsville Maintenance Dredging

Dredging operations including the design and construction of dredge bunds pipeline.

Charles Point Patches

Ports & Harbours

Charles Point Patches

Dredging to increase the depth of a shipping channel in Darwin, NT.