Fortescue Metals Group (FMG) has gained a licence for Port Towage Services for the iron ore export terminal at Port Hedland, Western Australia and is constructing infrastructure for tugs. Hall Contracting has been awarded the contract of dredging adjacent Anderson Point for the construction of the tug facility.

The scope of works comprises dredging of the Tug Facility extent and approach channel from end of AP3 Berth. The volume of material to be dredged for this development is a nominal 0.8 million cubic metres. Hall Contracting’s CSD’s Eastern Aurora and Mabuiag will dredge the material to the designated design level of the Tug Infrastructure pocket, approach channel and benched areas. All dredged material will be reclaimed onshore to the Designated Material Management Area.

#Project Data

  • LOCATION

    Port Hedland, Western Australia

  • CLIENT

    Pilbara Marine Pty Ltd

#Related Projects

Condabri Central and Reedy Creek APLNG

Energy Resources & Mining

Condabri Central and Reedy Creek APLNG

Construction and installation of gas and water gathering pipelines.

FMG Port Facility Tailings Pond Dredging

Energy Resources & Mining

FMG Port Facility Tailings Pond Dredging

Dredging of approximately 4.5 million cubic metres from tailings ponds.

Hail Creek Mine Tailings Dredging

Energy Resources & Mining

Hail Creek Mine Tailings Dredging

Dredging of approximately 280,000m³ of sediment for Hail Creek Mine.

BLCP Project – Map Ta Phut Thailand

Energy Resources & Mining

BLCP Project – Map Ta Phut Thailand

The removal of mud and silts from ponds on the site of the future BLCP power station.