Developer Stockland engaged Hall to deliver a 65-metre-long reinforced concrete weir for the Lake Kawana Rowing Lake.
The team carried out extensive temporary bunding works to construct the weir, as well as 23,000m3 of earthworks.
The project also involved installing 704m3 of concrete structures, 416m2 of steel sheet-pile cut-off walls, and rock scour protection.